In some of my organization projects, some resources don't have a PC. So I
would like the Unit Managers to update actual work for all the activities of
theyr unit, even though they are not assigned to that work. They only have
to manage that activity.
In Project Web Access the resource can only update the actual work for
activities they have been assigned to, so I can't find a solution!
Please help!
Mauro
would like the Unit Managers to update actual work for all the activities of
theyr unit, even though they are not assigned to that work. They only have
to manage that activity.
In Project Web Access the resource can only update the actual work for
activities they have been assigned to, so I can't find a solution!
Please help!
Mauro