Update Actual work

L

Laura

hello, probably my question will be strange for intensive user of project
server 2007..sorry but i'm still kinda new of it.

I have some problem in managing actual work insert from my team member.
They submit their timesheets to me weekly.
they import actual work to my task page and then submit also this page.

Then I accept their actual work on the project but sometimes something
strange happens: some of their actual work is different from what is written
oh timesheet and on details on my task page.

I'll give you an example:
my team member inserts on a task of a project in TIMESHEET
tuesday 6h
wednesday 4h
then he imports and sumbits on MY TASK page

when i view the impact on the project then I saw (on the line of ACTUAL WORK):
monday 1,38h
tuesday 5,62h
wednesday 0h

why does project do this? is it linked to the type of the task?
someboby can help me?

thank you very very much!
 
L

Laura

Dear Gary,
the system administrator tol me
Version: 12.0.6219.1000
HTH

is it right?
i'm going crazy to adjust this problem when it happens..
thank you very much!
 
R

Renke Holert [MVP]

Hi,

there has been a bug for resource's calendars others than the project's
calendars:

http://support.microsoft.com/kb/952000

Hope this helps,

Renke

--
Renke Holert [Project MVP]
https://mvp.support.microsoft.com/profile=1EC8A95A-A5FC-48D7-AE21-1AA67C09BF17

Autor von Microsoft Office Project 2007 - Das Profibuch
http://www.amazon.de/Microsoft-Office-Project-2007-CD-ROM/dp/3866454104/holertcom

MS Project Beratung, Training und Entwicklung - Oldenburg/Bremen - München
http://www.holert.com

Planung und Zeiterfassung mit MS Project, Lotus Notes, Outlook und Exchange
Server
http://www.allocatus.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top