Richard Millard
Hi,
I have a user of Project Web Access that updates his time using the PWA web
interface. He then clicks "Update All", but this is not automatically
notifying the project administrator that there are updates available.
He first has to open up MS Outlook and select a task that has been imported
from Project, then click "Update Project Server". (He is using the Outlook
add-in.) He only has to do this for one task, then the project
administrator is notified of all the timesheet updates.
Is there some way to fix this? Not everyone is experiencing this behaviour,
but the "Update All" button on Project Web Access does not work for him.
Thanks,
Richard
I have a user of Project Web Access that updates his time using the PWA web
interface. He then clicks "Update All", but this is not automatically
notifying the project administrator that there are updates available.
He first has to open up MS Outlook and select a task that has been imported
from Project, then click "Update Project Server". (He is using the Outlook
add-in.) He only has to do this for one task, then the project
administrator is notified of all the timesheet updates.
Is there some way to fix this? Not everyone is experiencing this behaviour,
but the "Update All" button on Project Web Access does not work for him.
Thanks,
Richard