The MS Project Server 2003 implemention uses managed time periods to report
time on a weekly basis. When a resource enters time across multiple weeks
(Week1 and Week2 for example) and uses the update all button for week2, MS
Project Server submits only the hours entered for week2 to the resource
manager for Approval while the hours for week1 and week2 are submitted to the
project manager. Is there a work around for this?