What is the Status Date for your project : you set the Status Date in
Project / Project Information.
The "Update as scheduled" icon calculates the "% Complete" for each task
which has some remaining duration at the left (in the past) of the status
date.
What is the Status Date for your project : you set the Status Date in
Project / Project Information.
The "Update as scheduled" icon calculates the "% Complete" for each task
which has some remaining duration at the left (in the past) of the status
date.
What %... hare you using :
- % Complete (% of duration)
- % Work Complete (% of Work)
- Physical % complete
The first one must work fine, even if there is no resource assigned !
Gérard Ducouret
-----Original Message-----
Hello Jay,
What is the Status Date for your project : you set the Status Date in
Project / Project Information.
The "Update as scheduled" icon calculates the "% Complete" for each task
which has some remaining duration at the left (in the past) of the status
date.
icon. Imagine my surprise (not) when the task updated
correctly. Another MS gremlin?