Update as scheduled

J

jay fuller

Does anyone know why when you click on the "update as
scheduled" icon that the % complete columns do not update?
 
G

Gérard Ducouret

Hello Jay,

What is the Status Date for your project : you set the Status Date in
Project / Project Information.
The "Update as scheduled" icon calculates the "% Complete" for each task
which has some remaining duration at the left (in the past) of the status
date.

Hope this helps,

Gérard Ducouret
 
J

Jay

-----Original Message-----
Hello Jay,

What is the Status Date for your project : you set the Status Date in
Project / Project Information.
The "Update as scheduled" icon calculates the "% Complete" for each task
which has some remaining duration at the left (in the past) of the status
date.

Hope this helps,

Gérard Ducouret

"jay fuller" <[email protected]> a écrit dans le message
de news: [email protected]... update?


.
The status date is current (12/16/03). The task is
10/1/03 - 1/23/04. This should return a result of ~60% but
I'm not getting any number
 
G

Gérard Ducouret

What %... hare you using :
- % Complete (% of duration)
- % Work Complete (% of Work)
- Physical % complete

The first one must work fine, even if there is no resource assigned !

Gérard Ducouret

-----Original Message-----
Hello Jay,

What is the Status Date for your project : you set the Status Date in
Project / Project Information.
The "Update as scheduled" icon calculates the "% Complete" for each task
which has some remaining duration at the left (in the past) of the status
date.

Hope this helps,

Gérard Ducouret

"jay fuller" <[email protected]> a écrit dans le message
de news: [email protected]... update?


.
The status date is current (12/16/03). The task is
10/1/03 - 1/23/04. This should return a result of ~60% but
I'm not getting any number
 
G

Guest

-----Original Message-----
What %... hare you using :
- % Complete (% of duration)
- % Work Complete (% of Work)
- Physical % complete

The first one must work fine, even if there is no resource assigned !

Gérard Ducouret

"Jay" <[email protected]> a écrit dans le message de [email protected]...

10/1/03 - 1/23/04. This should return a result of ~60% but
I'm not getting any number


.
% Complete, but it is not calculating anything
 
G

Guest

-----Original Message-----

.
I copied the data into a new task and then chose the
icon. Imagine my surprise (not) when the task updated
correctly. Another MS gremlin?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top