Update baseline 1 from PSI

R

Radu

Hi,

For keeping track of tasks updates i implemented the following model:
1. Set initial baseline on project
2. Set baseline 1 on project
3. When user needs more time to finish the task, he requests task duration
update from PM - this is infopath form.
4. If PM approves, the task duration is changed and baseline 1 is updated
with current value - this should be done from infopath using PSI.
5. From timesheets users can change tasks duration entering remaining work.

In this way PM can track the initial duration, approved changed duration and
actual duration at any time.

How can i change/update project/task baseline 1 from an Infopath form (new
task duration approval form) ?

Thank you
 
D

Dale Howard [MVP]

Radu --

I already answered your original question. There is no need to continually
repost your questions! Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top