update baseline

M

med111

hello ,

it is really urgent!
I want to know if it is possible to update baseline with the use of
PSI ?
I thought that I can use projectUpdate method but I found out that
baseline property is missed in ProjectDataSet.Task.
In other hand, I found baseline field in the reportingDB. but updating
data in DB directly is not good !

Any idea please?
 
R

Rod Gill

A possible reason you can't do this via PSI is that it shouldn't be done
from a process point of view so Microsoft excluded it (on the other hand
they might have forgotten it!!). Baselines should only be set in a schedule
at an agreed and known point. For example after the schedule for the next
iteration or phase has been agreed.

If you do want to set a baseline for all projects that don't have a baseline
set already because the process and training isn't in place then use VBA
from an Admin account to open each project, and save the baseline.

--

Rod Gill
Project MVP

Project VBA Book, for details visit:
http://www.projectvbabook.com

NEW!! Web based VBA training course delivered by me. For details visit:
http://projectservertraining.com/learning/index.aspx
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top