Is there a way to update the percentage complete and have the date
adjust to the new project end date?
Example: i have some tasks that are not supposed to start until may,
but there has been some work done on them. is there an easy way to
update the % complete and have the date move in since the task should
now finish sooner.
Is there a macro or some button i can use?