Update CostRateTable for a Resource Assignment

S

Scott Simms

Hi,

Can anyone suggest a way to update the 'CostRateTable' field for an
Assignment?

Thanks,

Scott.
 
J

Jan De Messemaeker

Hi,

Manually, in either Usage View you can insert the column Cost Rate Table
Or double-click the assignment and enter it in the assignment information
form

In VBA, as assignmentobject.costratetable (0 for A, 1 for B, etc.)

Hope this helps,
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
S

Scott Simms

Thanks for your feedback. Sorry I forget to mention that I am wanting to
update the 'CostRateTable' field via PSI in Project Server 2007.

Thanks,

Scott.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top