Sebastian Cordoba
Hello everyone!
I need the Team Members to Update a Custom field (Date) and send it as part
of the report, using "My Tasks" section.
I've done this test: 1- Created a Date Custom field (at task level); 2-
Added the new field to "My Assignments" view; 3- In "My Tasks" I updated this
field (and the progress) for a task and sent the report; 4- Approved the
update.
But when I open the Project via MPP and add the custom field to the table,
the value remains as "NA".
What should I do to allow the Team Members to update this field properly?
Thank you.
I need the Team Members to Update a Custom field (Date) and send it as part
of the report, using "My Tasks" section.
I've done this test: 1- Created a Date Custom field (at task level); 2-
Added the new field to "My Assignments" view; 3- In "My Tasks" I updated this
field (and the progress) for a task and sent the report; 4- Approved the
update.
But when I open the Project via MPP and add the custom field to the table,
the value remains as "NA".
What should I do to allow the Team Members to update this field properly?
Thank you.