Update Dates

S

Sarah A

Is it possible to move forward all tasks within a project by several weeks,
rather than going into each task and moving the start and finish dates
individually?
 
M

Mike Glen

Hi Sarah,

Welcome to this Microsoft Project newsgroup :)

On the Analysis tool bar, click the Adjust Dates macro button.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 