We have a number of projects which are out of synch with timesheets (too many
fingers in the pot). I was assisting a PM by changing a field in his project.
After saving, I mindlessly clicked Yes to synch with timesheets, thereby
clearing out manually entered updates. Setting aside the fact that people
shouldn't have been entering changes manually (it wasn't the PM, so he has no
idea what they were), I have a problem. The PM had just accepted updates from
timesheets, so there are significant changes since the last backup.

Question: If we restore the project from backup, the next time the PM
accepts updates from timesheets, will it pull in ALL timesheet information,
or just the new not previously accepted information (assuming he DOES NOT
synch with timesheets when prompted)?

Thanks,
 
M

Marc Soester

Mike,

I have not tested it, ( so you need to test it), but I assume that you will
loose the accepted time.
 