Using MSP2003 ENT,

I need to change the Task information on my Enterprise global template.
Under Task information-Advanced-Task type I would like to change the task
type to Fixed Duration, then save the template so all users have this option.
 
D

Dale Howard [MVP]

Reuter --

Setting the Task Type value in the Enterprise Global will NOT set this value
for each of your project managers. Remember that the Enterprise Global is
your organization's "library" of custom objects, such as Fields, Views,
Tables, Filters, Groups, etc. It is NOT the location in which to specify
Options settings for each project manager's Microsoft Project application.
Instead, you need to specify the values you want set in Tools - Options, and
then mandate that your project managers set these options. It is a training
and performance issue, therefore. Hope this helps.
 