Scot --
This functionality isn't a bug, by the way. According to Microsoft, this
functionality is by design because it keeps the current day of the week
centered in the middle of the timesheet grid. Because this is tripping up
users, however, Microsoft will modify the default behavior of the timesheet
grid in a future Service Pack or hotfix to lock the first day of the
timesheet on the first day of the reporting period. Hope this helps.
Dear Dale,
You are THE BEST !!!!
Pearl
"Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com> wrote in
message
- Show quoted text -
Hi Pearl,
Just so you know, there is a bug in the logic for the Show Hours Per
Day portion of the My Tasks web-part. Once this is turned on the
current period (work-week) doesn't calculate properly. The incorrect
logic for the webpart will only displays 3 days before and 3 days
after whatever the current date is. So you can never get the entire
work-week to display correctly in this view except for one day
depending on when your work-week starts in Project Server.
This is so very confusing to end-users and has caused a number of
clients to experience users duplicating their time entries or
recording time against tasks on the wrong day. I have subsequently
shot this functionality off at two clients that had requested it until
a hot-fix is released to fix the issue.
Regards,
Scot