Hi,
We are working with Project Pro. & Server 2007.
We use the "update project" feature to reschedule uncompleted work to start
after...on a weekly cycle.
After doing so, we level the resources on the plan to get the new "picture"
of the schedule.
The problem is, that when leveling resource is performed, it takes back to
the past some of the rescheduled tasks.
We don't use status date at all, which means it gets the default of the
actual day we're at when leveling.
The weekly cycle takes every Sunday (week start in Israel), if matters
anything, and the calendars are defines to match it.
Can anyone shed light here?
Thanks,
Yaara.
We are working with Project Pro. & Server 2007.
We use the "update project" feature to reschedule uncompleted work to start
after...on a weekly cycle.
After doing so, we level the resources on the plan to get the new "picture"
of the schedule.
The problem is, that when leveling resource is performed, it takes back to
the past some of the rescheduled tasks.
We don't use status date at all, which means it gets the default of the
actual day we're at when leveling.
The weekly cycle takes every Sunday (week start in Israel), if matters
anything, and the calendars are defines to match it.
Can anyone shed light here?
Thanks,
Yaara.