I
Iain Carlin
I have the following scenario:
1. MS Project & Server 2003
2. Users entering Actual Hours and Remaining hours via timesheet
3. Project Manager does "Update Project Progress" to import the actuals to
the Project.
4. During the time the PM is updating/reviewing the entries to approve, a
Resource enters more actuals in their timesheet.
5. Once the Update is completed by the PM, the new entries by the Resource
are gone and the actuals are lost.
Is this a bug or do I have some settings wrong. I would think that Update
Project Progress should just process the items the PM has accepted and leave
any new actuals entered alone?
Iain Carlin
1. MS Project & Server 2003
2. Users entering Actual Hours and Remaining hours via timesheet
3. Project Manager does "Update Project Progress" to import the actuals to
the Project.
4. During the time the PM is updating/reviewing the entries to approve, a
Resource enters more actuals in their timesheet.
5. Once the Update is completed by the PM, the new entries by the Resource
are gone and the actuals are lost.
Is this a bug or do I have some settings wrong. I would think that Update
Project Progress should just process the items the PM has accepted and leave
any new actuals entered alone?
Iain Carlin