H
Hasaj Patrik
I have published the project plan on project server also with the assignemnt
for resources. They have written down their timesheet and press Save and
Submit.
The problem is that as the project ,managers I do not see any task update to
accept and move data into the project plan.
I have already approved the timesheet, but it did not help to solve this
problem ?
environment - Office Project Server 2007
thanks for any help
patrik hasaj
for resources. They have written down their timesheet and press Save and
Submit.
The problem is that as the project ,managers I do not see any task update to
accept and move data into the project plan.
I have already approved the timesheet, but it did not help to solve this
problem ?
environment - Office Project Server 2007
thanks for any help
patrik hasaj