Chris M
I am looking for information regarding the function, "Update Project". We
use an external tool, EPK to capture timesheet data. The software contains a
function to grab the project hours from the timesheets and apply the actuals
to the project schedule. We were just recently told to fully show the impact
of the actual hours charged, we need to also do "Update Project". We were
told doing so would reschedule tasks that had not started and also reschedule
in progress tasks to reflect remaining work. I guess what I'm looking for is
clarification that this is an appropriate function to use and also would
appreciate a heads up of potential problems this could cause.
use an external tool, EPK to capture timesheet data. The software contains a
function to grab the project hours from the timesheets and apply the actuals
to the project schedule. We were just recently told to fully show the impact
of the actual hours charged, we need to also do "Update Project". We were
told doing so would reschedule tasks that had not started and also reschedule
in progress tasks to reflect remaining work. I guess what I'm looking for is
clarification that this is an appropriate function to use and also would
appreciate a heads up of potential problems this could cause.