J
Jesse
What's the best way to update a resources's calendar -- I'm using Project
Server 2007 and Project Pro 2007?
Someone with the adequate perm's can open the resource in the ERP and update
the resources calendar.
A resource can enter time on vacation and other out of office activities in
the resources PWA Timesheet....but this requires that Timesheets be created.
Is there other ways to update a resource calendar? What's the best/easiest
way?
Server 2007 and Project Pro 2007?
Someone with the adequate perm's can open the resource in the ERP and update
the resources calendar.
A resource can enter time on vacation and other out of office activities in
the resources PWA Timesheet....but this requires that Timesheets be created.
Is there other ways to update a resource calendar? What's the best/easiest
way?