K
Kuku
I am a beginner in using Microsoft project and project server (2007).
My questions are as below:
1. I did create 2 user in PWA(Project Manager(PM) and Team member (Mr. A)).
PM publish a project schedule to PWA which all tasks in the project asssigned
to Mr. A. How Mr. A check his task and update the % of work complete?
-I tried login as Mr. A and I only found those tasks can add into "My Time
Sheet" but not in "My Task". The button in "My Task" to import time sheet was
disabled.
2. How PM track the project status?
-I tried use local MS Project 2007 connect to server then goto Collaborate
Request Progress Information but seem no different from the baseline plan
compare with the actual progress.
My questions are as below:
1. I did create 2 user in PWA(Project Manager(PM) and Team member (Mr. A)).
PM publish a project schedule to PWA which all tasks in the project asssigned
to Mr. A. How Mr. A check his task and update the % of work complete?
-I tried login as Mr. A and I only found those tasks can add into "My Time
Sheet" but not in "My Task". The button in "My Task" to import time sheet was
disabled.
2. How PM track the project status?
-I tried use local MS Project 2007 connect to server then goto Collaborate
Request Progress Information but seem no different from the baseline plan
compare with the actual progress.