When I update a task that was estimated to take one day but was completed the
same day as the start date, I lose the bar on the gantt chart. It shows the
duration as "0" and the bar disappears. If I change the actual to "hours",
it changes the finish date to the next day. But I want the start and finish
days to be the same and still view the bar on the gantt chart.