M
MarkR
Hello:
(I cannot seem to Google the answer to this simple question. Apologies if
it's an FAQ.)
I have a non-critical task #123 with no predecessors, set to begin on
January 1st, with a constraint to finish no later than January 30th. On
January 15th, when I open up Project to update progress, that task has still
not begun.
What is the best practice recommended way to ask Project to update
everything, so that my printout I take to the team members reflects that
task #123 will actually start somewhere between [today] and [finish no later
than], assuming that's still possible?
In essence, I want Project to update scheduled start dates to reflect
reality.
Is this a feature I'm overlooking? I know I could manually change the start
dates, but I would rather that Project updates them everywhere. Resource
Levelling doesn't seem to factor in today's date. Should I change the
project start date to today?
(An example of what task #123 might be is "Buy pens and pencils" for my new
business. There's no real predecessor to buying it, it's not critical, it's
not high priority, it's just another small task that is finish-to-finish
with the overall project.)
Thank you for any help.
/m
(I cannot seem to Google the answer to this simple question. Apologies if
it's an FAQ.)
I have a non-critical task #123 with no predecessors, set to begin on
January 1st, with a constraint to finish no later than January 30th. On
January 15th, when I open up Project to update progress, that task has still
not begun.
What is the best practice recommended way to ask Project to update
everything, so that my printout I take to the team members reflects that
task #123 will actually start somewhere between [today] and [finish no later
than], assuming that's still possible?
In essence, I want Project to update scheduled start dates to reflect
reality.
Is this a feature I'm overlooking? I know I could manually change the start
dates, but I would rather that Project updates them everywhere. Resource
Levelling doesn't seem to factor in today's date. Should I change the
project start date to today?
(An example of what task #123 might be is "Buy pens and pencils" for my new
business. There's no real predecessor to buying it, it's not critical, it's
not high priority, it's just another small task that is finish-to-finish
with the overall project.)
Thank you for any help.
/m