Update tasks externally??

U

UMAN

I am trying to updated a task externally in 2007 and in 2003 all i had to do
was set the project_ext_edited to 1 and set the EXT_EDIT_REF_DATA on the task
= to 1. Well in 2007 EXT_EDIT_REF_DATA is gone. What flag do i have to set
to make my update work?

Thanks
 
U

UMAN

Well i need to make actual cost timephased and i am not able to use VBA and i
also noticed that you can make actual cost timephased using the PSI. I was
able to do this in 2003 by making direct database table updates. Is there a
way i can do this in 2007, or do you have any suggestions for me in
completing this task of making actual cost timephased.

Thanks!
 
U

UMAN

in my second message i meant to say i saw that you CANNOT make actual cost
timephased using the PSI.
 