G
Gracie
Hello,
I'm trying to update a timesheet in Project Server, and
having some difficulty. I have multiple tasks assigned
to a particular team member within a project. When they
open their timesheet, they can enter actual work and
remaining work for some of these tasks, but not for all
of the tasks. In fact, they can not even type data in
the ActiveX control for some of these tasks. (I've
specified that resources update actual and remaining time
via PWA).
I've tried the same thing as the administrator, using the
Adjust Actuals function, with the same result. The cells
in the ActiveX control for these tasks are grayed out,
where others allow entry.
Has anyone seen this type of behavior before?
I'm trying to update a timesheet in Project Server, and
having some difficulty. I have multiple tasks assigned
to a particular team member within a project. When they
open their timesheet, they can enter actual work and
remaining work for some of these tasks, but not for all
of the tasks. In fact, they can not even type data in
the ActiveX control for some of these tasks. (I've
specified that resources update actual and remaining time
via PWA).
I've tried the same thing as the administrator, using the
Adjust Actuals function, with the same result. The cells
in the ActiveX control for these tasks are grayed out,
where others allow entry.
Has anyone seen this type of behavior before?