No. This is Microsoft Project 2003 Standard
The "Update to Schedule" button on the "Tracking" toolbar doesn't bring the % complete on a task up to today's date when pressed. In fact, it decreases the % complete to an arbitary value
----- Sean wrote: ----
PBG
If I understand you correctly, you are unable to update
project progress from within Project Pro? If so, contact
your administrator to get access. Access to
publish/update is by default granted to Administrators,
Portfolio Managers and Project Managers
Hope this helps
---------------------
Sean Pale
EPM Solutions Grou
Bennett Adelso
www.bennettadelson.co
-----Original Message----
The "Update to Schedule" button doesn't work in Project
2003. Is there a setting in the Options that needs to be
checked before that button is activated