Hi Team
In this moment I need your help about update the Work Billable to Work
NonBIllable in a lot of task in Timesheet.
I think that the best practice in this case is Update the table
MSP_TimesheetActual, and remove the data from the Field ACTUALWORKBILLABLE
and update the field ACTUALWORKNONBILLABLE with the last data.
The problem is that I don't now what another tables I need update to execute
this without problems in the future...
Can you Help me???
Luis Mata
In this moment I need your help about update the Work Billable to Work
NonBIllable in a lot of task in Timesheet.
I think that the best practice in this case is Update the table
MSP_TimesheetActual, and remove the data from the Field ACTUALWORKBILLABLE
and update the field ACTUALWORKNONBILLABLE with the last data.
The problem is that I don't now what another tables I need update to execute
this without problems in the future...
Can you Help me???