Hello,
My resources update work per day and reminaing work.
I planed a 5 days task. 8 hours for each day.
At the first day, the resources update only 5 hours actual work.
Now, the other days gets automatically more than 8 hours, to complete the 40
hours at 5 days.
The Project create a situation that the resource has overallocation.
BTW. The task type is fixed work.
Any idea ?