I am the PM for project A. I assign Task 1 to John doe.
John Doe logs into PWA and under My Tasks he sees the task I assigned
him
John updates his progress from 0% to 50% and then saves and submites
his update
I get an email notice about the change and go to the Task Updates
section on PWA and see the submitted change
I accept the change.
I then open project in Project Profesional and the change is not
reflected.
I go back to the Task Update screen review the audit log of past
changes and republish the update.
Still not reflected in the Project Plan. I review the project in PWA
same thing. I close everything and reopen. Still shows 0%.
Any ideas what I am doing wrong?
John Doe logs into PWA and under My Tasks he sees the task I assigned
him
John updates his progress from 0% to 50% and then saves and submites
his update
I get an email notice about the change and go to the Task Updates
section on PWA and see the submitted change
I accept the change.
I then open project in Project Profesional and the change is not
reflected.
I go back to the Task Update screen review the audit log of past
changes and republish the update.
Still not reflected in the Project Plan. I review the project in PWA
same thing. I close everything and reopen. Still shows 0%.