Random question here and I couldn't find a clear answer for. I'm
making a PSI call to UpdateProjectWorkspaceAddress to update the URL
of an existing publish project. I checked the queue and everything
was successfull (even the "Reporting (WSS Sync)"). However, when I
check the reporting DB, the workspace URL is null. If I check the
Publish DB, I can see the subweb name plain as day. I've also tried
the same senerio via PWA (created a project, published it without a
workspace, went into server settings-->Project Workspaces and created
a workspace for the project there). Same result. The Reporting DB
has the workspace as null while the Published DB has it there plain as
day.
The easy fix is to just re-publish the project, but is this how
UpdateProjectWorkspaceAddress suppose to work or did I just find a
bug?
-Christina
making a PSI call to UpdateProjectWorkspaceAddress to update the URL
of an existing publish project. I checked the queue and everything
was successfull (even the "Reporting (WSS Sync)"). However, when I
check the reporting DB, the workspace URL is null. If I check the
Publish DB, I can see the subweb name plain as day. I've also tried
the same senerio via PWA (created a project, published it without a
workspace, went into server settings-->Project Workspaces and created
a workspace for the project there). Same result. The Reporting DB
has the workspace as null while the Published DB has it there plain as
day.
The easy fix is to just re-publish the project, but is this how
UpdateProjectWorkspaceAddress suppose to work or did I just find a
bug?
-Christina