D
Daniel McG
We are currently still experimenting with Project and PWA. I have installed
the add-in for outlook to sync to PWA. When people are updating tasks from
outlook or PWA, it doesn't always update to the project. I have added a rule
in the Task update section to just approve all of the tasks when they flow
in, but even that has to be run every time I get an update, even though I
have it to run all the time. There are times when I will go into the Project
Properties and it will say that I need to publish and save because of
updates. At times that doesn't update the project itself. Any help would be
greatly appreciated!
the add-in for outlook to sync to PWA. When people are updating tasks from
outlook or PWA, it doesn't always update to the project. I have added a rule
in the Task update section to just approve all of the tasks when they flow
in, but even that has to be run every time I get an update, even though I
have it to run all the time. There are times when I will go into the Project
Properties and it will say that I need to publish and save because of
updates. At times that doesn't update the project itself. Any help would be
greatly appreciated!