Updates go to the wrong person

S

Shah

Product: MS project 2003
Project type: administrative project
I assigned a number of resources to a task called "meetings". As result the
updates from the PWA come to me, but i am not the PM. I can change the task
owner via Collaborate-> Republish Assignments .... but this works if there is
only one PM. The updates must go to 3 PMs: from resource A to PM 1, from
resource B to PM 2 and from resource C to PM 3. How can I arrange this?
 
G

Gary L. Chefetz [MVP]

Shah:

You need to have the appropriate project managers republish the assignments
for their resources only. You can accomplish this by applying the Using
Resource filter in an assignment-level view in project.
 
S

Shah

Thanks Gary!

Gary L. Chefetz said:
Shah:

You need to have the appropriate project managers republish the assignments
for their resources only. You can accomplish this by applying the Using
Resource filter in an assignment-level view in project.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top