Product: MS project 2003
Project type: administrative project
I assigned a number of resources to a task called "meetings". As result the
updates from the PWA come to me, but i am not the PM. I can change the task
owner via Collaborate-> Republish Assignments .... but this works if there is
only one PM. The updates must go to 3 PMs: from resource A to PM 1, from
resource B to PM 2 and from resource C to PM 3. How can I arrange this?