Updates tab: showing all outline levels

J

Joel P.

On the Updates tab in PWA, I can only see the Project Name level and the
task. I have tasks with several levels, and would like to see each level
listed. Even when I select all Outline levels, it still only displays the
Project name and the task level. Suggestions?

thanks,

Joel P.
 
D

Dale Howard [MVP]

Joel P --

There's no way around this little problem. It is a limitation of Project
Server. Sorry.
 