Upgrade to 2007 and problems with milestones

J

Jim Whiteford

I was just upgraded to project 2007. I just opened one of the projects that
was developed in 03 and I am finding that the tasks that were entered
previously as milestones no longer show as a single day but a range even
though the tasks are still showing up as milestones. How can this be fixed to
going back to reflecting just the single day?
 
D

Dale Howard [MVP]

Jim --

Set the Duration of each Milestone task to 0 days. Hope this helps.
 
J

Jim Whiteford

Hello Dale,

The duration is set to zero and the task has the "milestone" check box chosen.
 
J

Jim Whiteford

Dale-

the schedule is currently set as "Schedule from: Project Finish Date.

Could this be affecting it? It worked fine showing a milestone date as a
single day and not a range in 2003.
 
D

Dale Howard [MVP]

Jim --

Hmmm. What happens if you change the Schedule From value to Project Start
Date? Do the milestone problems go away? Let us know. Thanks!
 
J

Jim Whiteford

Yes they do but then that creates other problems elsewhere.

I did find that if I insert 1 minute instead of leaving it a milestone it
works properly as schedule from finish date.
 
D

Dale Howard [MVP]

Jim --

Well, I'm blanking. I have never seen the behavior you describe with
milestones. Perhaps someone else in this newsgroup can take a stab at
solving your problem. Sorry I can't be of more help to you. :(
 