Greetings all.
We recently upgraded to MS Project Pro 2007 SP1 from MS Project 2003.
A few people are now reporting problems with their task names. It
appears that the information about the task is still in the plan, but
the task names have disappeared. It does not seem to be a problem
with formating of the column size or the font.
Has anyone else faced this issue and been able to resolve it?
-Carol
We recently upgraded to MS Project Pro 2007 SP1 from MS Project 2003.
A few people are now reporting problems with their task names. It
appears that the information about the task is still in the plan, but
the task names have disappeared. It does not seem to be a problem
with formating of the column size or the font.
Has anyone else faced this issue and been able to resolve it?
-Carol