J
Jim Aksel
We maintain two separate project files, let's call them "Level3" and
"Level4". The structure of the two files is intended to be identical, but is
not exactly so. The Level 4 schedule is a further breakdown of everything in
the Level 3.
So, what is a "Task" in Level3 becomes a Summary Task in Level4. We are
resource loading with Work and real headcount on Level4. It will be EV based
on either %Work Complete or Physical%Complete.
What we want to do is take the %Work Complete data from the summary tasks of
Level4 and map them to the associated tasks in Level3.
Is there a way to do this?
One suggested solution was to just collapse Level4 to look like Level3.
However, that will not work. Our customer insists there be no hidden detail
in the Level3 schedule.
Any ideas?
"Level4". The structure of the two files is intended to be identical, but is
not exactly so. The Level 4 schedule is a further breakdown of everything in
the Level 3.
So, what is a "Task" in Level3 becomes a Summary Task in Level4. We are
resource loading with Work and real headcount on Level4. It will be EV based
on either %Work Complete or Physical%Complete.
What we want to do is take the %Work Complete data from the summary tasks of
Level4 and map them to the associated tasks in Level3.
Is there a way to do this?
One suggested solution was to just collapse Level4 to look like Level3.
However, that will not work. Our customer insists there be no hidden detail
in the Level3 schedule.
Any ideas?