Uploading Projects

S

Sue C

When uploading a project to server through the Wizard, and you come to
the screen with Task Name and Base Calendar. The Base Calendar is
showing None. Should this be changed to Standard for all the tasks?
 
D

Dale Howard [MVP]

Sue C --

You do not need to specify any calendar since the Project Calendar controls
the initial task schedule of all tasks in the project. Hope this helps.
 
S

Sue C

Dale,

I know it's a small thing to be answered. But thanks so much for
taking the time. We're doing our initial upload to Server, and
sometimes it's these little things that get you stuck.

Sue C
 
D

Dale Howard [MVP]

Sue C --

I compliment you for importing existing production projects into your
Project Server system. Doing so allows you to make sure the project
conforms to all of your organization's project, resource, task, and calendar
standards. Congrats! And you are more than welcome for the help. :)
 