URGENT!!! Actual Work

M

madrigal

I´m using MSProjectServer2003. The problem here is that the value in the
Actual Work field in my office projects is not the same that the value in
Project Web Access. It seems like the hours reported during the last week
didn´t get reported in PWA. But there´s something more curios, if I look at
the value of Actual Work for the whole project in the Menu of Projects in
PWA I can see the value that I´m lookingfor, I mean, the Total of Actual Work
is correct, but if I saw the detail for Actual Work for each task and sum the
values in the field, they didn´t match with the Total.
So... What's going on!!!
I really, really, appreciate if someone could help me with this trouble. It
has never happened before. Any idea about it?
Thanks in advance.
 
K

Kay Doggett

I have seen this happen when web time has not been posted back to project
either by the project managers or a problem on the project server that runs
the scripts. A project server I administered had a problem with the service
that runs the xml updates stopping and the tempdb on the sql server would max
out. It may not be the same thing, but those are suggestions.
 