M
madrigal
I´m using MSProjectServer2003. The problem here is that the value in the
Actual Work field in my office projects is not the same that the value in
Project Web Access. It seems like the hours reported during the last week
didn´t get reported in PWA. But there´s something more curios, if I look at
the value of Actual Work for the whole project in the Menu of Projects in
PWA I can see the value that I´m lookingfor, I mean, the Total of Actual Work
is correct, but if I saw the detail for Actual Work for each task and sum the
values in the field, they didn´t match with the Total.
So... What's going on!!!
I really, really, appreciate if someone could help me with this trouble. It
has never happened before. Any idea about it?
Thanks in advance.
Actual Work field in my office projects is not the same that the value in
Project Web Access. It seems like the hours reported during the last week
didn´t get reported in PWA. But there´s something more curios, if I look at
the value of Actual Work for the whole project in the Menu of Projects in
PWA I can see the value that I´m lookingfor, I mean, the Total of Actual Work
is correct, but if I saw the detail for Actual Work for each task and sum the
values in the field, they didn´t match with the Total.
So... What's going on!!!
I really, really, appreciate if someone could help me with this trouble. It
has never happened before. Any idea about it?
Thanks in advance.