When PM's created a specific project they set the start date to 3/14/07 and
the finish to 11/14/07 with a resultant work of 1000.75 hours. At some point
the baseline start date was set to 3/14/07 and the finish to 5/9/08, the
hours however are still 1000.75. The baseline hours in the OLAP are
2,851.0h. This project has been re-published with the baseline work at
1000.75. Is baseline work recalulated in the OLAP based upon the baseline
start and finish dates or can the work be overwritten in Project and then
re-published?