URGENT! Baseline work in Project and the OLAP cube are different

H

hinesa

When PM's created a specific project they set the start date to 3/14/07 and
the finish to 11/14/07 with a resultant work of 1000.75 hours. At some point
the baseline start date was set to 3/14/07 and the finish to 5/9/08, the
hours however are still 1000.75. The baseline hours in the OLAP are
2,851.0h. This project has been re-published with the baseline work at
1000.75. Is baseline work recalulated in the OLAP based upon the baseline
start and finish dates or can the work be overwritten in Project and then
re-published?
 
D

Dale Howard [MVP]

Ava --

You will not see the Baseline Work information change in the OLAP cube until
after the system rebuilds the OLAP cube. Can you confirm that the OLAP cube
has been rebuilt after publishing the project? Let us know.
 
H

hinesa

Sorry,I took so long but other more pressing requirements came into play. I
have refreshed the cube and this still shows this way. My question is really
whether there are cacluations done at the time of the creation of the cube,
or if the cube reflects only data (calculations included) that is entered
into project.
 