hinesa
Hello,
I have a project that was created with a start date of 3/4/07 and a finish
date of 11/14/07. The baseline work and the work values are 1000.75. This
project has been published and re-published to the server. The values in
Portfolio Analyzer are 1568 for both work and baseline work. What I am
doing wrong???
I have a project that was created with a start date of 3/4/07 and a finish
date of 11/14/07. The baseline work and the work values are 1000.75. This
project has been published and re-published to the server. The values in
Portfolio Analyzer are 1568 for both work and baseline work. What I am
doing wrong???