J
joshroberts
I'm using Microsoft Project 2000 and trying to schedule a project to end on
the deadline. When I change the rule to end on the deadline date, some of my
resources are overallocated due to this change. I realize this is happening
because the constraints are now finish as late as possible but is there any
way around this? If not, is there any other method by which I could schedule
my project so that it will end on the deadline and start as late as possible?
Thanks for your help.
the deadline. When I change the rule to end on the deadline date, some of my
resources are overallocated due to this change. I realize this is happening
because the constraints are now finish as late as possible but is there any
way around this? If not, is there any other method by which I could schedule
my project so that it will end on the deadline and start as late as possible?
Thanks for your help.