Sumit
Hi...
I have tasks with task type as fixed duration.
While importing data for assignments for that task I notice that the
DURATION gets AUTOMATICALLY changed in 2 cases:-
1) When I am importing actual effort for assignment
or
2) When I import actual start date for that assignment( assignment doesn't
have actual finish date as of now).
I am not able to find the logic why MSP is doing that.
Any help or insight into the behavior is really appreciated!!
Thanks a lot in advance!!!
I have tasks with task type as fixed duration.
While importing data for assignments for that task I notice that the
DURATION gets AUTOMATICALLY changed in 2 cases:-
1) When I am importing actual effort for assignment
or
2) When I import actual start date for that assignment( assignment doesn't
have actual finish date as of now).
I am not able to find the logic why MSP is doing that.
Any help or insight into the behavior is really appreciated!!
Thanks a lot in advance!!!