Urgent : Duration getting automatically changed

S

Sumit

Hi...

I have tasks with task type as fixed duration.

While importing data for assignments for that task I notice that the
DURATION gets AUTOMATICALLY changed in 2 cases:-

1) When I am importing actual effort for assignment
or
2) When I import actual start date for that assignment( assignment doesn't
have actual finish date as of now).

I am not able to find the logic why MSP is doing that.

Any help or insight into the behavior is really appreciated!!

Thanks a lot in advance!!!
 
J

Jan De Messemaeker

Hi,

When a task is 100% complete it seems to lose its property of fixed duration
and automatically revert to Fixed Units: modifying Actual Work changes
duration, not units.
Pity.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
S

Sumit

Yes,

By actual effort I mean Work in Hours

By actual start date for that assignment i do not mean actual dates for task.
I meant actual dates of Resources that are assigned to a particular tasks.

Any insight why MSP is changing duration automatically would be really
helpful.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top