dilipn123
Greetings!
I have setup Project 2007.
I have created 2 Enterprise Custom fields (for Entity Task) based on 2
custom lookup tables one named, "Activities" and another named
"SubActivities." Now, when I'm creating the tasks (through Project
Professional 2007), I choose the values for the custom lookup
"Activities" and "Sub Activities". Then, I save it and Publish the
project to Project Server 2007. Once, this is done, In the Project
Center, I can see the "Activities", "Sub-Activities" properly
populated, but when I go to My Tasks menu (View Assignments),
Activities and Sub-Activities are not populated? Could anybody let me
know why this is happening?
Thanks and Regards,
Dilip
I have setup Project 2007.
I have created 2 Enterprise Custom fields (for Entity Task) based on 2
custom lookup tables one named, "Activities" and another named
"SubActivities." Now, when I'm creating the tasks (through Project
Professional 2007), I choose the values for the custom lookup
"Activities" and "Sub Activities". Then, I save it and Publish the
project to Project Server 2007. Once, this is done, In the Project
Center, I can see the "Activities", "Sub-Activities" properly
populated, but when I go to My Tasks menu (View Assignments),
Activities and Sub-Activities are not populated? Could anybody let me
know why this is happening?
Thanks and Regards,
Dilip