Urgent-Enterprise Custom Fields not getting populated in PWA 2007

D

dilipn123

Greetings!

I have setup Project 2007.

I have created 2 Enterprise Custom fields (for Entity Task) based on 2
custom lookup tables one named, "Activities" and another named
"SubActivities." Now, when I'm creating the tasks (through Project
Professional 2007), I choose the values for the custom lookup
"Activities" and "Sub Activities". Then, I save it and Publish the
project to Project Server 2007. Once, this is done, In the Project
Center, I can see the "Activities", "Sub-Activities" properly
populated, but when I go to My Tasks menu (View Assignments),
Activities and Sub-Activities are not populated? Could anybody let me
know why this is happening?

Thanks and Regards,
Dilip
 
M

med111

Greetings!

I have setup Project 2007.

I have created 2 Enterprise Custom fields (for Entity Task) based on 2
custom lookup tables one named, "Activities" and another named
"SubActivities." Now, when I'm creating the tasks (through Project
Professional 2007), I choose the values for the custom lookup
"Activities" and "Sub Activities". Then, I save it and Publish the
project to Project Server 2007. Once, this is done, In the Project
Center, I can see the "Activities", "Sub-Activities" properly
populated, but when I go to My Tasks menu (View Assignments),
Activities and Sub-Activities are not populated? Could anybody let me
know why this is happening?

Thanks and Regards,
Dilip


Hi Dilip,
I have the same issue.
when creating a customl field , you should set the option
"Calculation for Assignment Rows " : "Roll down, unless manually
specified " .

this can solve your problem. But , unfortunetely it will be the cause
of other problem.
if you will use an assignement owner for many assignement on the same
task : you will have an error on My Tasks View

Hope that will help and let we know.

if anyone has any comment, he will be welcome.

bye
 
L

Lars Hammarberg

You're creating task fields, but looking at assignment data...
In project pro - select the Task usage view and the fields you created and
notice the difference.


/Lars Hammarberg
www.camako.se
MS Gold Partner
 
D

dilipn123

Hey med,

Tx buddy. I set the option for "calculation of assignment rows". Now,
my custom fields are propaged across my tasks and my timesheet views.
The second problem, I'm yet to encounter. I will let you know once I
get it.
Tx again. Have a good day!

Thanks and Regards,
Dilip
 