Hi All,
We had our project plan published on our EPM Server and actuals were being
reported against them. Later on arrived a need for removing the old plan and
publshing a new one. So a copy of the published plan was sent to the project
manager and was modified by him. Then we had the old plan removed from the
EPM Server. After that when we tried to upload the modified plan, project
server failed to recognize the enterprise resources already added for the
project and suggested to change the names of the resources and made them into
local ones and we did so.
Plan was successfully published. Now when we try to replace a local resource
to the old enterprise resource, it does not allow it, saying actuals have
been reported for the local resource.
Problem is we dont want to remove the actuals before replacing the resource
as the enterprise resource is the same who reported those actuals.
Please tell us what to do.
We had our project plan published on our EPM Server and actuals were being
reported against them. Later on arrived a need for removing the old plan and
publshing a new one. So a copy of the published plan was sent to the project
manager and was modified by him. Then we had the old plan removed from the
EPM Server. After that when we tried to upload the modified plan, project
server failed to recognize the enterprise resources already added for the
project and suggested to change the names of the resources and made them into
local ones and we did so.
Plan was successfully published. Now when we try to replace a local resource
to the old enterprise resource, it does not allow it, saying actuals have
been reported for the local resource.
Problem is we dont want to remove the actuals before replacing the resource
as the enterprise resource is the same who reported those actuals.
Please tell us what to do.