J
J Burford Fields
Hi again,
Project Help, when I search on PERT gives me a list of subjects
including the one on the subject line, above.
It provides instructions (below) to add a PERT Toolbar. Danged if I
can find a PERT toolbar. Any clues?
"You can perform a Program, Evaluation, and Review Technique (PERT)
analysis to estimate a task's (task: An activity that has a beginning
and an end. Project plans are made up of tasks.) duration.
"Perform a PERT analysis by using the default weights for duration
estimates
"On the View menu, point to Toolbars, and then click PERT Analysis.
"On the PERT Analysis toolbar, click PERT Entry Sheet .
"For each task, enter the optimistic, expected, and pessimistic
durations in the Optimistic Dur., Expected Dur., and Pessimistic Dur.
fields, respectively.
"If a task's duration is not expected to vary, enter the expected
duration in all three fields.
"Click Calculate PERT to calculate the estimated durations.
"Microsoft Office Project 2003 estimates a single project duration
based on a weighted average of the three duration values for each
task.
"To view the optimistic, expected, and pessimistic durations, on the
PERT Analysis toolbar, click Optimistic Gantt , Expected Gantt , or
Pessimistic Gantt .
"To view the end dates of the three resulting schedules, on the Tools
menu, click Options.
"Click the View tab, and then select the Show project summary task box
Project Help, when I search on PERT gives me a list of subjects
including the one on the subject line, above.
It provides instructions (below) to add a PERT Toolbar. Danged if I
can find a PERT toolbar. Any clues?
"You can perform a Program, Evaluation, and Review Technique (PERT)
analysis to estimate a task's (task: An activity that has a beginning
and an end. Project plans are made up of tasks.) duration.
"Perform a PERT analysis by using the default weights for duration
estimates
"On the View menu, point to Toolbars, and then click PERT Analysis.
"On the PERT Analysis toolbar, click PERT Entry Sheet .
"For each task, enter the optimistic, expected, and pessimistic
durations in the Optimistic Dur., Expected Dur., and Pessimistic Dur.
fields, respectively.
"If a task's duration is not expected to vary, enter the expected
duration in all three fields.
"Click Calculate PERT to calculate the estimated durations.
"Microsoft Office Project 2003 estimates a single project duration
based on a weighted average of the three duration values for each
task.
"To view the optimistic, expected, and pessimistic durations, on the
PERT Analysis toolbar, click Optimistic Gantt , Expected Gantt , or
Pessimistic Gantt .
"To view the end dates of the three resulting schedules, on the Tools
menu, click Options.
"Click the View tab, and then select the Show project summary task box