B
Bud
It was suggested that I do the following for changing unit% on resource
assignments for my whole schedule.
Select all Tasks then click Assign Resources icon (or Alt+F10) then enter
The task type for almost every task is Fixed work.
I selected all my tasks on the Gantt Chart view by highlighting on the whole
Gantt chart. I than clicked Alt+F10. It brings up the dialog box. I than
enter let's say 100% starting at each resource at the top and enter 100%.
However, it does NOT keep the 100% as I move down through each resource
manually entering 100%. When I am done it only gives me the close option.
So...I close and than nothing changes.
What am I doing wrong?
assignments for my whole schedule.
Select all Tasks then click Assign Resources icon (or Alt+F10) then enter
100% for your resources. This will recalculate all durations as with fixed
Units Project will assume Work won't change.
The task type for almost every task is Fixed work.
I selected all my tasks on the Gantt Chart view by highlighting on the whole
Gantt chart. I than clicked Alt+F10. It brings up the dialog box. I than
enter let's say 100% starting at each resource at the top and enter 100%.
However, it does NOT keep the 100% as I move down through each resource
manually entering 100%. When I am done it only gives me the close option.
So...I close and than nothing changes.
What am I doing wrong?