When you customize an enterprise field type of cost say for tasks, is it possible to automatically adjust the value of the predefined "Cost" field which represents the total cost.
I just want to be able to store the cost related to some tasks like
"Travel Expenses" and "accomodation" etc. where the total cost should calculate those values

Thx in advance!
 
G

Guest

You can't alter predefined fields. I suggest you
customise another cost field with a formula that
calculates the total cost (i.e. Cost + your travel
expenses + accomodation).
-----Original Message-----
When you customize an enterprise field type of cost say
for tasks, is it possible to automatically adjust the
value of the predefined "Cost" field which represents the
total cost.
I just want to be able to store the cost related to some tasks like
"Travel Expenses" and "accomodation" etc. where the total
cost should calculate those values
 
H

HZ

Thanks for your reply; however customizing a new Total cost field will not help because some other fields are dependent on the predefined cost field like the baseline, variance, remaining etc.

I thought of updating the Fixed Cost field instead, is there anyway to automatically calculate the custom fields and assign the value to the Fixed Cost?

Cheers!
 
H

HZ

Thanks for your reply; however customizing a new Total cost field will not help because some other fields are dependent on the predefined cost field like the baseline, variance, remaining etc.

I thought of updating the Fixed Cost field instead, is there anyway to automatically calculate the custom fields and assign the value to the Fixed Cost?

Cheers!
 
H

HZ

Thanks for your reply; however customizing a new Total cost field will not help because some other fields are dependent on the predefined cost field like the baseline, variance, remaining etc.

I thought of updating the Fixed Cost field instead, is there anyway to automatically calculate the custom fields and assign the value to the Fixed Cost?

Cheers!
 
H

HZ

Thanks for your reply; however customizing a new Total cost field will not help because some other fields are dependent on the predefined cost field like the baseline, variance, remaining etc.

I thought of updating the Fixed Cost field instead, is there anyway to automatically calculate the custom fields and assign the value to the Fixed Cost?

Cheers
 
H

HZ

Thanks for your reply; however customizing a new Total cost field will not help because some other fields are dependent on the predefined cost field like the baseline, variance, remaining etc.

I thought of updating the Fixed Cost field instead, is there anyway to automatically calculate the custom fields and assign the value to the Fixed Cost?

Cheers!
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top