M
Michael Thompson
I am interested in using Microsoft Project to represent production plans.
Specifically, I am interested in representing the flow of workpieces through
a series of machine tools/processes. I am interested in tracking the
utilization of the separate machines, human operators, materials, and other
resources. The various charting and reporting provided by Project would be
very helpful in order to optimize the process flow, identify bottlenecks, etc.
Unfortunately, I have not found this to be possible for at least two reasons:
1. Recurring tasks as implemented in Project do not represent true cyclic
tasks as the cycle periods cannot be specified in any unit less than days.
For example, a machine cycle time (duration) might be only 10-15 minutes and
might repeat on a period of 30 minutes.
2. Task repetitions may need to be specified using advanced rules. For
example, assume that I manufacture pieces in a continuous stream but choose
to inspect only one part out of every five. That means that I will have an
inspection task that should be triggered after every fifth part is machined.
I realize that Microsoft Project is a project planning tool and not a
production workflow planning tool. However, it has many of the features
needed to address production workflow planning. I am wondering if anyone
else has tried to use it in this way an, if so, how did you go about
overcoming the concerns noted above?
Specifically, I am interested in representing the flow of workpieces through
a series of machine tools/processes. I am interested in tracking the
utilization of the separate machines, human operators, materials, and other
resources. The various charting and reporting provided by Project would be
very helpful in order to optimize the process flow, identify bottlenecks, etc.
Unfortunately, I have not found this to be possible for at least two reasons:
1. Recurring tasks as implemented in Project do not represent true cyclic
tasks as the cycle periods cannot be specified in any unit less than days.
For example, a machine cycle time (duration) might be only 10-15 minutes and
might repeat on a period of 30 minutes.
2. Task repetitions may need to be specified using advanced rules. For
example, assume that I manufacture pieces in a continuous stream but choose
to inspect only one part out of every five. That means that I will have an
inspection task that should be triggered after every fifth part is machined.
I realize that Microsoft Project is a project planning tool and not a
production workflow planning tool. However, it has many of the features
needed to address production workflow planning. I am wondering if anyone
else has tried to use it in this way an, if so, how did you go about
overcoming the concerns noted above?