S
Simon L
It seems that the PDS tool does not allow an external system to: -
1. pass baseline data to MS P Server
2. pass cost data
3. does not display the project percentage complete
4. does not display the enterprise custom field values in PWA
Does anyone know an extender or something that would allow our inhouse
project management system (not MS Project) to pass its data to MS Project
Server 2003.
MSPServer2003 provides a useful enterprise gantt chart and management
reports via OLAP. We can pass basic data from our .NET app to the server but
much of the key data is missing (baselines, %ages etc). We would prefer not
to develop our own Gantt charts and olap cubes.
If we publish through MS Project desktop it works. Is Microsoft stopping
this deliberatly or can we get around the problem?
Anyone with any ideas?
Thanks in advance
1. pass baseline data to MS P Server
2. pass cost data
3. does not display the project percentage complete
4. does not display the enterprise custom field values in PWA
Does anyone know an extender or something that would allow our inhouse
project management system (not MS Project) to pass its data to MS Project
Server 2003.
MSPServer2003 provides a useful enterprise gantt chart and management
reports via OLAP. We can pass basic data from our .NET app to the server but
much of the key data is missing (baselines, %ages etc). We would prefer not
to develop our own Gantt charts and olap cubes.
If we publish through MS Project desktop it works. Is Microsoft stopping
this deliberatly or can we get around the problem?
Anyone with any ideas?
Thanks in advance