P
Peter Dunn
I have been reading the details of the Infrastructure Update as we want to
implement a timesheeting/task updating mechanism inside our Project Server
2007 environment.
I have been worried about getting staff to enter their actual work into PWA
because I wanted them to use a timephased grid interface to do so but I
didn't want them to have to use the existing My Timesheets sheet view and
ALSO the My Tasks view (via either (a) manual update of My Tasks, (b) Manual
importing of My Timesheets data to My Tasks or (c) use of the automatic
update of the My Timesheets data into My Tasks). To me, having to rely on
staff to update and synch and submit and get approved both of these was going
to be a recipe for creating two sets of unsynchronised truth (aka disaster)
no matter how vigilant we were.
With the IU I see that the My Tasks view has been enhanced to expose the
underlying timephased grid of data which is EXCELLENT. I am now of a mind to
centralise on ONLY this method of actual work entry so as to avoid any use of
the My Timesheets view. Note that we capture all time (including
administrative time such as leave, etc) as tasks within projects, and so have
no need for the special categories of time available in the TimeSheeting view.
But I expect that this decision isn't as simple as I am making it out to be
and that there may still be My Timesheets functionality that is not in the
timephased grid features of My Tasks.
So my question is ... what might this extra functionality be. That is, why
would I still want to consider having staff use both, when it might seem that
only My Tasks with the IU applied would be sufficient?
implement a timesheeting/task updating mechanism inside our Project Server
2007 environment.
I have been worried about getting staff to enter their actual work into PWA
because I wanted them to use a timephased grid interface to do so but I
didn't want them to have to use the existing My Timesheets sheet view and
ALSO the My Tasks view (via either (a) manual update of My Tasks, (b) Manual
importing of My Timesheets data to My Tasks or (c) use of the automatic
update of the My Timesheets data into My Tasks). To me, having to rely on
staff to update and synch and submit and get approved both of these was going
to be a recipe for creating two sets of unsynchronised truth (aka disaster)
no matter how vigilant we were.
With the IU I see that the My Tasks view has been enhanced to expose the
underlying timephased grid of data which is EXCELLENT. I am now of a mind to
centralise on ONLY this method of actual work entry so as to avoid any use of
the My Timesheets view. Note that we capture all time (including
administrative time such as leave, etc) as tasks within projects, and so have
no need for the special categories of time available in the TimeSheeting view.
But I expect that this decision isn't as simple as I am making it out to be
and that there may still be My Timesheets functionality that is not in the
timephased grid features of My Tasks.
So my question is ... what might this extra functionality be. That is, why
would I still want to consider having staff use both, when it might seem that
only My Tasks with the IU applied would be sufficient?