Users don't receive tasks to do, even there are in a project

O

OK

Hi,
I created a project in Project Pro 2007, built team from enterprise, assign
tasks to team members,
saved this project and did Collaborate - Request Progress Information

But only I received all these tasks as MINE !!!! I see all of them on my
task list, but with the name of my team members.

E-mail notification works fine. For status update request all team members
received and can fill it them.

What's wrong ? Please help. Working with Project 2003 I didn't have such
problems.
 
D

Dale Howard [MVP]

OK --

Whoever is your Project Server administrator missed a step in creating the
resources in Project Server 2007. He/she needs to specify a value in the
Default Assignment Owner field for each resource in the system. He/she must
specify this value from the Project Center page in PWA, and must do this for
each resource individually. He/she must select the resource's own name as
the Default Assignment Owner. This field determines who sees task
assignments in PWA. In your enterprise project, you can work around this
problem by temporarily inserting the Assignment Owner field in the Task
Usage view, and then selecting the name of each resource individually in
this field. After doing so, republish your project. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top